12-05-2023 10:28 AM - edited 25-07-2024 03:37 PM
Update: 25 July 2024
Our engineers have activated the mast onto the network this week, and full service has been restored to Thurnscoe. We will continue to monitor performance in the area.
Update: 11 July 2024
Over the past month, our engineers have experienced a slight delay activating the mast onto the network, due to circumstances outside of our control. Barring any further unforeseen delays, we expect the mast to be on air-by the end of July.
We will keep you updated on this post.
Update: 10 May 2024
Our engineers have installed the power supply at the site and we have been working with the fibre provider to agree a date to install the transmission needed for the new mast. We have experienced a slight delay arranging a date to access the area and expect the transmission to be installed by the middle of June. Barring any further unforeseen delays, we expect the mast to be on-air by the beginning of July.
We will keep you updated on this post.
Update: 04 March 2024
Over the past month, our engineers have been working with the site provider to access the area and install a power supply at the site, which we expect to be installed by the middle of March. We have been working with the fibre provider to agree a date to install the transmission needed for the new mast, and have arranged to access the area and complete the work needed by the end of May. Barring any unforeseen delays, we expect the mast to be on-air by the middle of June.
We will keep you updated on this post.
Update: 19 January 2024
Over the past few months, our engineers have been in negotiations with the fibre provider to agree a date they can access the area to install the transmission. Negotiations are ongoing and, once we have a date from the fibre provider and the transmission has been installed, we can confirm an approximate on-air date for the new mast.
We will keep you updated on this post.
Update: 12 October 2023
Over the past few weeks our engineers have completed building the equipment needed for the new mast. We are working with the fibre provider to arrange a date to install the transmission needed to integrate the mast onto the network. Once we have a date for the transmission to be completed, we can confirm an approximate on-air date.
We will keep you updated on this post.
Update: 15 September 2023
Over the past month our engineers have started building the equipment needed for the new mast and expect the build to be completed by the end of October. We have requested the transmission for the new mast from the fibre provider to integrate the mast onto the network. Once we have a date for the transmission to be completed, we can confirm an approximate on-air date.
We will keep you updated on this post.
Update: 07 August 2023
Our engineers are completing the final steps to start building the equipment for the new mast. Due to logistical issues with the deployment of the new site, we will be required to use an alternative transmission than originally planned to integrate the mast onto the network. Once the equipment has been built, our engineers can request the transmission needed for the new mast from the fibre provider and confirm an approximate on-air date.
We will keep you updated on this post.
Update: 20 July 2023
Over the past few weeks, the revised drawings have been approved by the site provider and our engineers can start building the equipment needed for the new mast. Due to circumstances out of our control, we have experienced a slight delay starting the build but, barring any further unforeseen delays, we expect this to be completed and the mast to be on-air by the middle of September.
We will keep you updated on this post.
Update: 22 June 2023
Over the past few weeks, our engineers have been requested to revise the drawings for the build. Pending a positive outcome from the revised drawings, we will start building the equipment needed for the new mast. Pending a positive outcome from the revised drawings, we expect to start building the equipment needed for the mast by early August, Once the equipment has been built, we can start integrating the mast onto the network and confirm an approximate on-air date for the new mast.
We will keep you updated on this post.
We are aware of a signal issue that is affecting some of our customers in the Thurnscoe area. Our mast in the area had to be removed from the existing site in May 2023, as this was requested by the landowner.
Our engineers began looking for a new location as soon as we were made aware our equipment had to be removed, and we have located a new area. We have completed the required designs and surveys to make sure the land will be suitable for the equipment, and our engineers have started to build the equipment needed for the new mast. Barring any unforeseen delays, we expect the build to be completed by the end of June. Once the equipment has been built, we can start integrating the mast onto the network and confirm an approximate on-air date for the new mast.
We will keep you updated on this post.
We’re sorry for any inconvenience caused. In the meantime, you may be able to use WiFi Calling to make and receive calls and texts over a WiFi connection.
For information on who can use WiFi Calling and how to set up this service, please see our Using WiFi Calling Help page.
24-06-2023 06:20 AM - edited 24-06-2023 07:11 AM
Hi
Can you tell me,once this new mast is installed and is back online up and running.... are we going to get 5g in the area.??, ... Will it be switched back on as a 4g, or 5g connection??
I'd assume,that new equipment, would be the latest equipment and while their at it as such,make all the upgrades.
I see the mast is actually erected (22/6/23) I assume that is the new mast at Bottom of Lidget Lane???but was advised at the call centre it would be August before Activated.
Is that right,another 2 months even the mast is installed ???
I was mis-sold my more expensive Handset/Contract as advised this is newest and best for me being a 5g device.I live in a 4g area so it would never have worked In the first place.Been told there nothing can be done to revert that contract.
I also consume around 10% month to month of the data I was advised I needed.
Also advised to use WiFi as a temporary measure,sure,great if I had Broadband, and also advised I can take out a 2 year broadband deal with a overall cost £600 odd pound on top of my worthless phone plan to put me on with for a couple of months.
I've had a credit rebate taken from my bill for a month,however this doesn't solve the issue of having a functioning phone unless I pay the fee for 2 years broadband I don't need,as well as the device/contract that wont provide 5g and I don't need !
My phone bill for 2x 5g handsets this month(may to June ) is .. get ready...Drun Roll.......£167!
It's not good enough
24-06-2023 06:26 AM
@TommyPixel Obviously you do or you wouldn’t be complaining on here. And of your going to reply to anyone at least use the @ key so they know.
03-07-2023 06:12 PM
hi thank you so how do I go about some compensation as I'm paying £143 a month for something I can't get full use out of
03-07-2023 06:34 PM
Hi @linzi41,
Please get in touch with Customer Care on 150 if you'd like to discuss your account.
Thanks
James
03-07-2023 07:16 PM
24-07-2023 11:22 PM
I live in s63
I've called 150 and had my "full" bill credited for 2x phones from May all the way to August, and to call back if and when it be nessary August to September.
IE: had best part of £400 refunded
In the meantime, I've bought a payg sim card for one of the other operators, begins with 0 and ends in 2,hot spotted using a old phone to connect my EE handsets ,plus Chromecast to it for iplayer etc... no problem at all WiFi calling or getting on line now...
I've vouched for putting up with the inconvenience, and holding out for EE rather than going elsewhere, generally I've found them pretty good at sorting stuff out and ive been with them 20 years ,a lot can depend on who you get at the call centre,but that's life...
Really hoping the new equipment whilst it's going in will bring 5g with it , will be worth hanging on for if it does than changing providers.
03-08-2023 02:47 PM
What's point in getting in contact they don't give a crap all they try and do is blame the the phone or the SIM card been having issues since April and been told it could be another 4 week's if not more and won't even be refunded for the poor service it's redicules
05-08-2023 06:56 AM
05-08-2023 07:08 AM
They don’t have to. They need to call up and mention trading standards if they genuinely can’t make or keep a call EE, will be able to see that and can give credits.
15-08-2023 06:53 PM
Hi Leanne,
is the timeline still for mid-September? The pub has been demolished mostly, just rubble to clear. I am assuming this mast is the build from the planning approval
This says the mast is both EE and H3M (Three). Is this correct?
Thanks