Coverage in Barnet

Leanne_T
EE Community Support Team

Update: 04 November 2026

Over the past few months, our engineers have submitted the drawings for approval. Pending a positive outcome from the drawings, we can start building the equipment needed for the temporary mast.   

We will keep you updated on this post.


Update: 11 August 2026

Over the past few weeks, the traffic management test has been completed. Our engineers are waiting for detailed drawings to be completed to submit these for approval. Pending a positive outcome from the drawings, we can start building the equipment needed for the temporary mast.   

We will keep you updated on this post.


Update: 16 July 2026

Over the past few months, our engineers have been continuing negotiations with the site provider for planning approval for the permanent mast.  Pending a positive outcome from the negotiations, we can start legal steps to legally acquire the land from the site provider and start

For the temporary mast, our engineers are working with the traffic management company to arrange a date to carry out the pressure test. Once the pressure test has been completed, the surveys will be submitted for approval. Pending a positive outcome from the surveys and tests, we can start building the equipment needed for the temporary mast.   

We will keep you updated on this post.


Update:  06 July 2026

For the past month, our engineers need to complete pressure tests of the area for the temporary mast, due to the location this will require traffic management. Once the pressure test has been completed, the surveys will be submitted for approval. Pending a positive outcome from the surveys and tests, we can start building the equipment needed for the temporary mast.   

We will keep you updated on this post.  


Update:  26 May 2026 

Over the past few weeks, for the temporary mast our engineers have started surveys at the area to make sure the area will be suitable for the equipment. Pending a positive outcome from the surveys, we can start building the equipment needed for the temporary mast. 

We will keep you updated on this post. 


Update: 24 April 2026 

Over the past few weeks, our engineers have been continuing negotiations with the site provider for planning approval for the first location. Pending a positive outcome from the negotiations, we can start legal steps to legally acquire the land from the site provider and start building the equipment needed for the new mast.  

Our engineers have located an area for a temporary mast to be installed and are working with the site provider to conduct surveys to make sure the area will be suitable for the equipment. 

We will keep you updated on this post. 


Update: 26 March 2026 

Over the past few days, our engineers have optimised some of the existing sites in the area to support customers that have been impacted from the removal of the existing mast.  

Our engineers are looking at other temporary options to restore service as quickly as possible to Barnet, whilst continuing with the surveys for a new permanent mast at the new location.  

We will keep you updated on this post.


We are aware of a signal issue that is affecting some of our customers in the Barnet area. Our mast in the area had to be removed from the existing site in March 2026, as the building is being redeveloped. 

Our engineers began looking for a new location as soon as we were made aware our equipment had to be removed. We have located an area for the new mast and are currently conducting surveys to make sure the location will be suitable for the equipment. Pending a positive outcome from the surveys, we can start legal steps to legally acquire the land from the site provider and start building the equipment needed for the new mast.

We will keep you updated on this post.

We’re sorry for any inconvenience caused. In the meantime, you may be able to use WiFi Calling to make and receive calls and texts over a WiFi connection. 

For information on who can use WiFi Calling and how to set up this service, please see our Using WiFi Calling, Help page.

122 REPLIES 122
KristianPappas
Visitor

Ee customer service is the worst. This issue is very annoying for many customers in the barnet area and everytime i call you, your answer is “Use Wifi Calling”. This is unacceptable, no solution is given, you are not allowing us to terminate the contract without a penalty and it is also taking you forever. There is a contract between ee and a customer for a reason. I am paying 20£ a month and you should provide your customer with the service agreed. We all have had enough, and even if you fix the problem, as soon as my contract ends i will leave this company 100% and never recommend to anyone. Shame on you EE

Rach_H
EE Community Support Team

Hi @KristianPappas,

Thanks for coming to the Community!

I'm sorry to hear you've been impacted by this, and understand how concerning this must be for you.

WiFi Caling is a great option to stay connected while this issue is ongoing, but if you aren't happy that this is happening then you can reach out to our team a log a complaint. If you aren't happy with the resolution our guide offers then you can ask for this to be escalated to a Team Leader.

Rach

In the context of this no signal business approaching a year, I’d love to know what about the new mast EE now say is being built is “temporary” - what’s the long term plan! Maybe in the year 2130 they will install a permanent one “once the designs have had their plans approved and can start work on building the equipment”